EIA reports for public comment

These reports are listed currently or were previously listed on the Department of Environmental Affairs ECC Portal https://eia.meft.gov.na/.

The dates indicate the last date that it was/will be possible to comment on the project on the portal.

You can also track the progress of EIAs in Namibia using the EIA Tracker website on https://eia-tracker.org.na and you can learn more about the EIA process in Namibia here.

Explore your search results using the filter checkboxes, or amend your search or start a new search.

Displaying results 901 - 950 of 5884Click/tap on any title to see full details of the record
Tuesday, 4 March 2025
Environam Consultants Trading (ECT) 2025. 250211005352: Renewal of the Environmental Clearance Certificate for the proposed township establishment on Portion 143 of Farm Townlands of Gobabis No. 114, Omaheke Region.

Gobabis is the capital of the Omaheke Region, and is situated approximately 200 kilometers from the capital city Windhoek. As the gateway to Botswana and Namibia’s major trading partner South Africa, Gobabis’ location along the Trans-Kalahari Corridor serves it well, as goods transported from the mines in Botswana to the port of Walvis Bay and those transiting through Botswana from South Africa contribute greatly to the growth of the town. The town lies approximately 110 kilometers from the Buitepos border post.

Saturday, 1 March 2025
2025. 240719004419: Mining project (Mining Claim 75205), Epembe, Kunene Region.
Extraction of mineral ore by open cast method a. Exploration b. Mining and ancillary works c. Mineral processing d. Construct accessory works and roads.
Thursday, 27 February 2025
Risk-Based Solutions (RBS) 2025. 250210005329: Application for Environmental Clearance Certificate (ECC) for the proposed subdivision of Farm Katima Mulilo Townlands No. RE/1328 into 18 Portions and the Remainder for allocation to His Royal Highness, Chief George Simasiku, Mafwe Traditional Authority.

The ECC is required by the Mafwe Traditional Authority for the Proposed Subdivision of Farm Katima Mulilo Townlands No. RE/1328 into 18 Portions and the Remainder for Allocation to His Royal Highness, Chief George Simasiku, Mafwe Traditional Authority, Chichimane Khuta, Katima Mulilo Townland, Zambezi Region.The proposed development comprises the following: Eight (8) residential plots, one (1) General residential, eight (8) business and one (1) truck port plots supported by a 15 m wide pipeline servitude (Fig. 2.1).

Thursday, 27 February 2025
Urban Green 2025. 250206005300: Application for the renewal of an Environmental Clearance Certificate (ECC-01990) for the construction and operation of the Kokerboom Photovoltaic Power Facility, Keetmanshoop District, //Karas Region.

The Renewal of the Environmental Clearance Certificate is for: Activity 1(a) - Energy Generation, Transmission and Storage Activities The construction of facilities for the generation of electricity (solar Power); Activity 1(b) - Energy Generation, Transmission and Storage Activities The construction of facilities for the transmission and supply of electricity (solar Power); Activity 5.1(c) - Land Use and Development Activities Agricultural use to industrial use 2. Details of the Activity(s) covered by the Environmental Clearance Certificate: 2.1.

Thursday, 27 February 2025
Urban Green 2025. 250206005299: Application for the renewal of an Environmental Clearance Certificate (ECC - 02072) for the construction and operation of the Hardap Photovoltaic Power Facility, Mariental District, Hardap Region.

The Renewal of the Environmental Clearance Certificate is for: Activity 1(a) - Energy Generation, Transmission and Storage Activities The construction of facilities for the generation of electricity (solar Power); Activity 1(b) - Energy Generation, Transmission and Storage Activities The construction of facilities for the transmission and supply of electricity (solar Power); Activity 5.1(c) - Land Use and Development Activities Agricultural use to industrial use 2. Details of the Activity(s) covered by the Environmental Clearance Certificate: 2.1.

Thursday, 27 February 2025
Namibia Water Corporation (NamWater) 2025. 241030004876: Application for Environmnetal Clearance Certificate for the Olushandja Water Treatment Plant upgrade and extension project.
The proposed upgrade and extension of the Olushandja Water Treatment Works in Omusati Region. Namwater has an existing water treatment plant at Olushandja which has aged and is approaching its lifespan. It is against this background that Namwater would like to upgrade and extend the existing plant to meet the demand for Ruacan, Onesi, Tsandi and Etunda for the next seventeen years. The new plant will be built on the existing site that belongs to Namwater at Olushandja.
Monday, 24 February 2025
Geo Pollution Technologies 2025. 250204005284: Closure and subdivision of a public open space, and rezoning to utility services, on Erf 2998, Naraville, Walvis Bay, Erongo Region.
The project involves the acquisition of ownership of the land on which Erongo RED's electrical distribution substation is located. The scope of the project includes the subdivision of Erf 2998, currently designated as public open space, and its subsequent rezoning to align the land use with the operational requirements of the substation. Subdivision will allow the demarcation of the substation's footprint, while rezoning ensures compliance with municipal land-use regulations. These steps are required to secure legal ownership and to enable Erongo RED to manage and operate the site effectively.
Monday, 24 February 2025
Geo Pollution Technologies 2025. 250204005283: Closure and subdivision of a public open space, and rezoning to utility services, on Erf 2799, Walvis Bay, Erongo Region.
The project involves the acquisition of ownership of the land on which Erongo RED's electrical distribution substation is located. The scope of the project includes the subdivision of Erf 2799, currently designated as public open space, and its subsequent rezoning to align the land use with the operational requirements of the substation. Subdivision will allow the demarcation of the substation's footprint, while rezoning ensures compliance with municipal land-use regulations. These steps are required to secure legal ownership and to enable Erongo RED to manage and operate the site effectively.
Monday, 24 February 2025
Geo Pollution Technologies 2025. 250204005282: Closure and subdivision of a public open space, and rezoning to utility services, on Erf 2067, Naraville, Walvis Bay, Erongo Region.
The project involves the acquisition of ownership of the land on which Erongo RED's electrical distribution substation is located. The scope of the project includes the subdivision of Erf 2067, currently designated as public open space, and its subsequent rezoning to align the land use with the operational requirements of the substation. Subdivision will allow the demarcation of the substation's footprint, while rezoning ensures compliance with municipal land-use regulations. These steps are required to secure legal ownership and to enable Erongo RED to manage and operate the site effectively.
Monday, 24 February 2025
Geo Pollution Technologies 2025. 250204005281: Closure and subdivision of a public open space, and rezoning to utility services, on Erf 2046, Walvis Bay, Erongo Region.
The project involves the acquisition of ownership of the land on which Erongo RED's electrical distribution substation is located. The scope of the project includes the subdivision of Erf 2046, currently designated as public open space, and its subsequent rezoning to align the land use with the operational requirements of the substation. Subdivision will allow the demarcation of the substation's footprint, while rezoning ensures compliance with municipal land-use regulations. These steps are required to secure legal ownership and to enable Erongo RED to manage and operate the site effectively.