EIA reports for public comment

These reports are listed currently or were previously listed on the Department of Environmental Affairs ECC Portal https://eia.meft.gov.na/.

The dates indicate the last date that it was/will be possible to comment on the project on the portal.

You can also track the progress of EIAs in Namibia using the EIA Tracker website on https://eia-tracker.org.na and you can learn more about the EIA process in Namibia here.

Explore your search results using the filter checkboxes, or amend your search or start a new search.

Displaying results 5801 - 5850 of 6161Click/tap on any title to see full details of the record
Friday, 14 August 2020
Namibia Environmental Consultants (NEC) 2020. APP-001475: The construction and operation of WT Fuel Centre (Truck Port) on Erf 546 in Katima Mulilo.

The Environmental Clearance Certificate is for the construction and operation of the WT Fuel Center (Truck Port) in Katima Mulilo. The site area is located on the premises of Roads Contractor Company (RCC) in Katima Mulilo. The site has previously been used by RCC to fill up their construction machinery and as a result, there is already an underground diesel tank. The tank has a capacity of 82000 Litres and the current proponent will make use of the same tank.

Thursday, 13 August 2020
Stubenrauch Planning Consultants 2020. APP-001674: Environmental Assessment for the Subdivision of the Remainder of Portion 49 of the Consolidated Farm Tsumore No. 761 into Portions A- E and Remainder, and creation, Tsumeb, Oshikoto Region.

The environmental clearance certificate is for: Activity 10.1 (b) Infrastructure The construction of Public roads Activity 10.2 (a) Infrastructure The route determination of roads and design of associated physical infrastructure where - it is a public road The proponent intends to subdivide the Remainder of Portion 49 of the Consolidated Farm Tsumore No. 761 into Portions A - E and Remainder. Currently portion D accommodates the existing rubbish dump of the Municipality while Portions A - C, E and the Remainder is currently vacant.

Thursday, 13 August 2020
NamPower 2020. APP-001670: The operation of the 66KV Gerus-Platveld Transmission Line.

The ECC is for the operation of the 66kV Gerus - Platveld transmission line in Otjozondjupa Region. The 66kV Gerus - Platveld line was constructed prior to the commencement of the Environmental Management Act and its regulation, as a result there was no environmental impact assessment study conducted for the project prior to its development. It is therefore against this background that NamPower intends to apply for the operational Environmental Clearance Certificate in order to comply to the Environmental Management Act (Act 7 of 2007) and its regulations.

Thursday, 13 August 2020
NamPower 2020. APP-001667: The operation of the 66KV Gerus-Paresis Transmission Line in Otjozondjupa Region.

The ECC is for the operation of the 66kV Gerus - Paresis transmission line. The 66kV Gerus – Paresis line was constructed in 1999 prior to the commencement of the Environmental Management Act and its regulation, as a result there was no environmental impact assessment study conducted for the project prior to its development. It is therefore against this background that NamPower intends to apply for the operational Environmental Clearance Certificate in order to comply to the Environmental Management Act (Act 7 of 2007) and its regulations.

Thursday, 13 August 2020
SLR Environmental Consulting (Namibia) 2020. APP-001680: Renewal Application: Environmental Clearance Certificate for the amendment to the Arandis Power Thermal Power Generation and Waste Oil Recycling Plant, Erongo Region.

Renewal application: The renewal of Arandis Power’s Environmental Clearance Certificate (ECC) for the Amendment to the Arandis Power Thermal power generation and waste oil recycling plant, Erongo Region (i.e. Renewal Application for: Arandis Power 120MW Heavy Fuel Oil (HFO) power plant and the associated solar photovoltaic power plant).

Wednesday, 12 August 2020
SLR Environmental Consulting (Namibia) 2020. APP-001104: Environmental Performance Report and Management Plan for water abstraction boreholes on Farm Finsterbergen WW 205370 (BH1), WW 205368 (BH2), WW 205369 (BH3), WW 205367 (BH4), and WW 205371 (BH5).

Farm Finsterbergen No. 469 (Farm Finisterbegen) managed by Mr. Siegfried Kuhn is located 30 km north-west of Otavi and 40 km south west of Tsumeb, in the Otjozondjupa Region. The farm was previously owned by Finsterbergen Holdings CC as an irrigation farm and it has since 2017 been bought over by Marabu Trading (PTY) Ltd (Marabu Trading) also for the purposes of conducting an irrigation scheme.

Tuesday, 11 August 2020
NamPower 2020. APP-001673: The operation of the 66KV Otjiwarongo-Matemba Transmission Line in Otjozondjupa Region.

The ECC is for the operation of the Otjiwarongo - Matemba transmission line. 66kV Otjiwarongo - Matemba line was constructed prior to the commencement of the Environmental Management Act and its regulation, as a result there was no environmental impact assessment study conducted for the project prior to its development. It is therefore against this background that NamPower intends to apply for the operational Environmental Clearance Certificate in order to comply to the Environmental Management Act (Act 7 of 2007) and its regulations.

Tuesday, 11 August 2020
Stubenrauch Planning Consultants 2020. APP-001581: Subdivision of Erf 3108 (of Erf 101), Okahao Proper into 12 erven and Remainder, Okahao, Omusati Region.

The proponent intends to rezone Erf 3108 from Government to Undetermined after which it will be subdivided into 12 Erven and Remainder. The proposed subdivision will create 11 Residential erven and 1 Public Open Space. The proposed subdivision will also provide for the creation of a 12-meter-wide street.

Monday, 10 August 2020
LM Environmental Consulting 2020. APP-001596: Environmental Management Plan for the Chobe Savanna Lodge, Zambezi Region, Namibia.

Environmental Management Plan for the Chobe Savanna Lodge, Zambezi Region, Namibia Existing Tourism Establishment (Chobe Savanna Lodge was built in 1999; the present owner, Caprivi Fly Fishing Safaris (Pty) Ltd T/A Chobe Savanna Lodge, purchased the property in 2008).

Monday, 3 August 2020
Stubenrauch Planning Consultants 2020. APP-001623: Environmental Assessment for the Subdivision, Permanent Closure and Rezoning of Erf 599, Ondangwa Extension 1, Ondangwa.

The environmental clearance certificate is for: Activity 5.1 (d) (Infrastructure) The rezoning of land from use for nature conservation or zoned open space to any other land use. The proponent intends to subdivide Erf 599 into Erf A, B, C and Remainder. It is thus further the intention of the proponent to permanently close Erven A/599, B/599 and C/599, as Public Open Space in order to rezone Erf A/599 from Public Open Space to Office; Erf B/599 from Public open space to Civil and Erf C/599 from Public Open Space to Institutional.

Monday, 3 August 2020
Stubenrauch Planning Consultants 2020. APP-001624: Environmental Assessment for the Subdivision, Permanent Closure and Rezoning of Erf 332 Onethindi Extension 1, Oniipa, Oshikoto Region.

The environmental clearance certificate is for: Activity 5.1 (d) (Infrastructure) The rezoning of land from use for nature conservation or zoned open space to any other land use. The proponent aims to subdivide Erf 332 Onethindi Extension 1 into Erven A/332, B/332 and Remainder. Erf 332, Onethindi Extension 1 is currently owned by the Oniipa Town Council. The erf however accommodates JSN Automotive Groups business in the form of a car garage.

Monday, 3 August 2020
Stubenrauch Planning Consultants 2020. APP-001623: Environmental Assessment for the Subdivision, Permanent Closure and Rezoning of Erf 599, Ondangwa Extension 1, Ondangwa.

The environmental clearance certificate is for: Activity 5.1 (d) (Infrastructure) The rezoning of land from use for nature conservation or zoned open space to any other land use. The proponent intends to subdivide Erf 599 into Erf A, B, C and Remainder. It is thus further the intention of the proponent to permanently close Erven A/599, B/599 and C/599, as Public Open Space in order to rezone Erf A/599 from Public Open Space to Office; Erf B/599 from Public open space to Civil and Erf C/599 from Public Open Space to Institutional.

Monday, 3 August 2020
Stubenrauch Planning Consultants 2020. APP-001624: Environmental Assessment for the Subdivision, Permanent Closure and Rezoning of Erf 332 Onethindi Extension 1, Oniipa, Oshikoto Region.

The environmental clearance certificate is for: Activity 5.1 (d) (Infrastructure) The rezoning of land from use for nature conservation or zoned open space to any other land use. The proponent aims to subdivide Erf 332 Onethindi Extension 1 into Erven A/332, B/332 and Remainder. Erf 332, Onethindi Extension 1 is currently owned by the Oniipa Town Council. The erf however accommodates JSN Automotive Groups business in the form of a car garage.

Friday, 31 July 2020
LM Environmental Consulting 2020. APP-001456: Operation of the Kappsvalley Lodge, Farm Kappsvalley Farm No. 65, Windhoek Rural, Khomas Region.

To open Lodge for tourists, and to get registration from NTB.

Friday, 31 July 2020
SLR Environmental Consulting (Namibia) 2020. APP-001625: The renewal of the environmental clearance certificate for the Emulsion Manufacturing Plant at the Husab Mine.

Renewal Application: Continue operating the emulsion manufacturing plant, which stores and then mixes relatively inert chemicals and oils to produce an emulsified product for use in blasting. Swakop Uranium’s emulsion manufacturing plant at the Husab Mine, which stores and then mixes relatively inert chemicals (ammonium nitrate and sodium nitrate) and oils (used diesel and machine oil) to produce an emulsified product for use in blasting. The product from the plant is a non-explosive yellowish paste.

Friday, 31 July 2020
SLR Environmental Consulting (Namibia) 2020. APP-001626: The renewal of the environmental clearance certificate for the telecommunication transmitter mast at the Husab Mine.

Renewal Application: Continue operating the telecommunication transmitter mast (i.e. cell phone tower) to ensure effective communication for Swakop Uranium’s activities at the Husab Mine plant complex. Swakop Uranium required a telecommunication transmitter mast (i.e. cell phone mast) in order to meet communication requirements at their Husab Mine. As part of the original Husab Mine EIA and the EIA Amendment process, a 30 m high cell phone mast was described and assessed for radio and cell-phone communication repeaters to be installed on site near the plant complex.

Friday, 31 July 2020
NamPower 2020. APP-001631: The operation of the 220KV Auas - Hardap powerline in Khomas and Hardap Regions.

The ECC is for the operation of the 220 kV Auas - Hardap Powerline. The 220kV Auas-Hardap 1 & 2 powerlines were constructed prior to the commencement of the Environmental Management Act and its regulation, as a result there was no environmental impact assessment study conducted for the project prior to its development. It is therefore against this background that NamPower intends to apply for the operational Environmental Clearance Certificate in order to comply to the Environmental Management Act (Act 7 of 2007) and its regulations.

Friday, 31 July 2020
Tortoise Environmental Consultants (TEC) 2020. APP-00984: Environmental Management Plan for sand mining and brick making project.

Hilka Bricks and Garden Project is a brick making project that has been in operation since 2015. The project sources sand from an existing sandpile left from previous road works in the area. an Environmental Clearance Certificate is applied for as this was not obtained previously.

Thursday, 30 July 2020
Stubenrauch Planning Consultants 2020. APP-001517: Environmental Assessment for the Permanent Closure of Erf B (A Portion of Erf 825) St James Street measuring ± 3774 m2 in extent as a Street, Keetmanshoop, Karas Region.

It is then intension of the proponent to permanently close Erf B (A Portion of Erf 825) St James Street measuring ± 3774 m2 in extent as a Street. The proponent further intends to subdivide Erf 252 into Erf A and Remainder and further consolidate Erf A/252 with Erf B/825. The newly consolidated Erf will be rezoned from Local Authority to Business to be used for Business purposes. The subject site is located within a mixed land use area and would thus be suitable for the proposed development. The exact type of business to be developed on the site is not known.

Wednesday, 29 July 2020
Namibia Water Corporation (NamWater) 2020. APP-001614: Continuation of the Swakoppoort - Von Bach - Navachab Water supply scheme.

The application is for the renewal of an existing Swakoppoort - Von Bach - Navachab Water Supply Scheme ECC, issued in June 2017 for the above-mentioned project.

Wednesday, 29 July 2020
Namibia Water Corporation (NamWater) 2020. APP-001613: Continuation of the Goblenz Water supply scheme.

The application is for the renewal of an existing Goblenz Water Supply Scheme ECC, issued June 2017 for the above-mentioned project.

Wednesday, 29 July 2020
Namibia Water Corporation (NamWater) 2020. APP-001612: Continuation of the Berg Aukas Water supply scheme.

The application is for the renewal of an existing Berg Aukas Water Supply Scheme ECC, issued June 2017 for the above-mentioned project.

Wednesday, 29 July 2020
NamPower 2020. APP-001602: The operation of the 66KV Omaere-Gobabis transmission line in Omaheke Region.

The ECC is for the operation of 66kV Omaere - Gobabis transmission line. The 66kV Gobabis-Omaere line was constructed in 1995 prior to the commencement of the Environmental Management Act and its regulation, as a result there was no environmental impact assessment study conducted for the project prior to its development. It is therefore against this background that NamPower intends to apply for the operational Environmental Clearance Certificate in order to comply to the Environmental Management Act (Act 7 of 2007) and its regulations.

Wednesday, 29 July 2020
Risk-Based Solutions (RBS) 2020. APP-001611: Proposed Development of the Windhoek Waterfront Project Proposed Waterfront Project, along Goreangab Dam and a mix use Development including the Shopping Mall Rezoning and Closure of the Public Open Space, Windhoek, Khomas Region.

The application for Amendment to the Environmental Clearance Certificate (ECC) granted on the 5th December 2019 is to reflect the Proposed Shopping Mall Rezoning and Closure of the Public Open Space for the Proposed Windhoek Waterfront Development, Windhoek, Khomas Region Central Namibia. The amended ECC is required for proposed development of the Windhoek Waterfront Project , along Goreangab Dam and a mix use development including the shopping mall rezoning and closure of the public open town planning and design, preconstruction, construction, operation / commissioning stages.

Wednesday, 29 July 2020
Risk-Based Solutions (RBS) 2020. APP-001552: Proposed Mining and Ongoing Exploration in the Mining License (ML) No. 204, Karibib Project Karibib District, Erongo Region, Namibia.

he application for the renewal and transfer of the ECC from Desert Lion Energy (Pty) Ltd to Lepidico Chemicals Namibia (Pty) Ltd is for the proposed mining and ongoing exploration in the Mining License (ML) No. 204, Karibib Project, Karibib District, Erongo Region, Namibia. Proposed project lifecycle will cover preconstruction, construction, operation, monitoring and ongoing rehabilitation and mine closure decommissioning and aftercare stages.