APP-001611: Proposed Development of the Windhoek Waterfront Project Proposed Waterfront Project, along Goreangab Dam and a mix use Development including the Shopping Mall Rezoning and Closure of the Public Open Space, Windhoek, Khomas Region

Publication Year:
2020
Abstract:

The application for Amendment to the Environmental Clearance Certificate (ECC) granted on the 5th December 2019 is to reflect the Proposed Shopping Mall Rezoning and Closure of the Public Open Space for the Proposed Windhoek Waterfront Development, Windhoek, Khomas Region Central Namibia. The amended ECC is required for proposed development of the Windhoek Waterfront Project , along Goreangab Dam and a mix use development including the shopping mall rezoning and closure of the public open town planning and design, preconstruction, construction, operation / commissioning stages. The proposed project development covers the planning and design, preconstruction, construction, operation, and monitoring stages. The town planning and rezoning process as well as the activities of the planning and design, preconstruction and construction activities have already been implemented. The construction process will involve the following multiples Phase 1 to 3: Phase 1: 2019 - 2021 covering 150 standalone houses, 29 sectional title houses, 5 general residential plots, 6 business mixed-use plots and 2 public open spaces. Phase 2: 2020 - 2021: 58 standalone houses, 6 general residential plots, 7 business mixed-use plots, 2 public open spaces, and 1 institutional plot, and. Phase 3: 2021 - 2023: 10 standalone houses, 13 general residential plots, 5 business mixed-use plots, 1 municipal plot and 1 institutional plot. Following the completion of the construction activities that will be undertaken as part of the phased development process of the Windhoek Waterfront project, the following is the summary of the separate Phases 1 - 3 that will be implemented: Completion and commissioning; Operational; Monitoring and maintenance, and future extensions and infrastructure upgrades.

Item Type:
Report
Language:
en
Last date for commenting on this EIA: Wednesday, 29 July 2020

This EIA Report is/was listed currently or previously for Public Comment on the Department of Environmental Affairs ECC Portal http://eia.met.gov.na. You can search the eLibrary for all EIA reports for public comment here, track the progress of EIAs in Namibia using the EIA Tracker website on https://eia-tracker.org.na and you can learn more about the EIA process in Namibia here.